Indefinite Delivery Indefinite Quantity (IDIQ)
GreenTech shall provide complete architectural/engineering works and construction activities services at various Government facilities worldwide including but not
The project consists of the provision of a new Kandak for the Afghanistan National Army (ANA) in Faryab Province, Afghanistan. The site is located in The Qaysar District.The project is defined as the design, material, labor, and equipment to construct buildings, parking, utilities
The project consists of the provision of a new Kandak for the Afghanistan National Army (ANA) in Faryab Province, Afghanistan. The site is located in The Qaysar District.The project is defined as the design, material, labor, and equipment to construct buildings, parking, utilities and other infrastructure for the Afghanistan National Army.
Water System:
Design and construct a Potable Water System (PWS), to include a well, protected in an enclosed water well house, water well pump(s), steel or concrete ground storage tank (GST), booster pumps, expansion tank, hydro-pneumatic tanks, and an underground pipe distribution network system.
The storage tanks with minimum capacity of 150,000 liters which is 100 percent of the required daily demand based on 190 L/capita/day (50gal/capita/day).
Sanitary Sewer System and WWTP
Construction and design of Sanitary sewer collection system. Sewer collection system with gravity sewer pipe and appurtenances such as manholes, cleanouts and building service connections (lift stations and force mains lift station for the wastewater treatment plants.
The treatment system generally located at the low portion of the site, and consists of two (2) package wastewater treatment plants. These plants shall be installed so that their effluent is able to gravity flow to a designated point of disposal topographically below the plant.

GreenTech shall provide complete architectural/engineering works and construction activities services at various Government facilities worldwide including but not

The project is defined as the design, material, labor, and equipment to construct buildings, facilities, utilities and other infrastructure for the new plant; modify sewer collection system to re-route wastewater flow from the existing plant to the new plant; and restore existing plant site.

The nature of this project was Waste water treatment of “ANA BRIGADE FACILITIES-JALAL ABAD AFGAHNISTAN” that was designed in according with the influent quantity and quality of waste water and effluent criteria. The selected system for the treatment is chosen as pond.