Design and Construction of Camp Shaheen WWTP, Mazar-e-sharif , Afghanistan / 2009 - (W5J9JE-11-C-0074)

The project is defined as the design, material, labor, and equipment to construct buildings, facilities, utilities and other infrastructure for the new plant; modify sewer collection system to re-route wastewater flow from the existing plant to the new plant; and restore existing plant site.

Design and Construction of Camp Shaheen WWTP, Mazar-e-sharif , Afghanistan / 2009 - (W5J9JE-11-C-0074)

  • Client: US Army Corps of Engineers
  • Prime: Omran Holding
  • Sub Contractor: Green Tech

This Design Build project consists of the design and construction of a new wastewater treatment plant for a population of 24,000 at Camp Shaheen in Mazar E Sharif in Afghanistan ANA base. The project is defined as the design, material, labor, and equipment to construct buildings, facilities, utilities and other infrastructure for the new plant; modify sewer collection system to re-route wastewater flow from the existing plant to the new plant; and restore existing plant site. The project included the following features of work:

Narrative

  • Electrical Power Connection(s) and Distribution Network
  • Sanitary Sewer Collection System Modifications
  • Water Supply Connection and Distribution System
  • Site Communication System
  • Access Road, Road Network, Walkways, Parking
  • Perimeter Fence w/Access Gates
  • Decommissioning and Demolition of Existing Wastewater Treatment Plant and Abandoned Lift Stations
Design and Construction of a new Wastewater Treatment Plant to include:
  • Influent Pump Station
  • Headwork
  • Administration/Laboratory/
  • Chlorination Bldg
  • Aeration and Settling Ponds
  • Polishing Pond w/
  • Water Tanker Filling Station
  • Plant Effluent Drainage Channel
  • Sludge Pump Station
  • Sludge Drying Beds
  • Storm water management system
  • Plant Startup and Operator Training

Design Parameters for the WWTP

Influent Characteristics of Wastewater:
  • BOD5 – 400 mg/L or based on 0.09 kilograms (0.20 pounds) per person per day whichever is greater loading
  • TSS –400 mg/L
  • TKN – 80 mg/L
  • Fecal Coliform – 108 MPN /100 mL

Effluent Criteria Limitations for Direct Surface Water Discharge:

  • BOD5
  • The 30-day average will not exceed 30 mg/L.
  • The 7-day average will not exceed 45 mg/L.
  • CBOD5 may be substituted for BOD5. In those cases the following limits will apply:
  • 30-day average will not exceed 25 mg/L.
  • The 7-day average will not exceed 40 mg/L.

Water Well Specification: installing equipment for well with yield of 14-l/s and upgrading two other wells to receive 42-l/s-flow.

  • Water Storage Tanks specification: one new water storage tank with volume of 840 cubic meter
  • Pump House Specification: a boosting package with capacity up to 130-l/s-flow
  • WTP type: chlorine disinfection
  • Sewer Collection Type: gravity sewer
  • WWTP Type: lagoon system
  • Unit of WWTP: aeration pond, setting pond, chlorination system, drying bed, lift stations and etc.

Leave a Reply

Your email address will not be published. Required fields are marked *

Recommended Articles

ANA Gamberi Garrison, Jalalabad, Afghanistan

The nature of this project was Waste water treatment of “ANA BRIGADE FACILITIES-JALAL ABAD AFGAHNISTAN” that was designed in according with the influent quantity and quality of waste water and effluent criteria. The selected system for the treatment is chosen as pond.

Read More