KANDAHAR AIR WING (KAW) WATER AND WASTE WATER SYSTEM UPGRADE consisted of the Design &  construction for completion of the Kandahar Air Wing at Kandahar Province, Afghanistan

KANDAHAR AIR WING (KAW) WATER AND WASTE WATER SYSTEM UPGRADE (W5J9JE18C0004)-2019

  • Client: US Army Corps of Engineers
  • Prime: GreenTech

KANDAHAR AIR WING (KAW) WATER AND WASTE WATER SYSTEM UPGRADE consisted of the Design &  construction for completion of the Kandahar Air Wing at Kandahar Province, Afghanistan.

This project consisted of the specified site-adaptation, site design, infrastructure design, and construction of a partially constructed for the campus facility which will house approximately 3,500 personnel consisting of trainees and staff.

The project is defined as the design and construction of one wastewater treatment plant, one new well in a new well house, new water storage tanks, new water booster pump system in a new booster pump house, parking and

roads for the project area, utilities (water, electrical distribution, sewer lines), demolition and other infrastructure for a design population

of approximately 3500 personnel. Also included in this project is an optional new well with new well house, new water storage tanks, new booster pump system in a new booster pump house that shall be constructed if the Government exercised that option

Narrative

  • Average daily demand for a single person is 190 liter /day.
  • 80% of the domestic water usage converted to sewage flow.
  • The site population assumed to be 3000 people (+ 500 for future expansion).
  • For the analysis the flow assumed steady state.
  • The gravity sewer system assumes no pressure flow. The maximum depth of flow inside
  • The pipe not exceed 70% of the diameter of the pipe for building connections and 80% for laterals and main trunk lines.
  • The capacity factor was assumed to be 2.

Leave a Reply

Your email address will not be published. Required fields are marked *

Recommended Articles

ANA Gamberi Garrison, Jalalabad, Afghanistan

The nature of this project was Waste water treatment of “ANA BRIGADE FACILITIES-JALAL ABAD AFGAHNISTAN” that was designed in according with the influent quantity and quality of waste water and effluent criteria. The selected system for the treatment is chosen as pond.

Read More

Keep In Touch

Address

25214 LARKS TER, CHANTILLY, VA, 20152

Contact

571-337-1358

Email

info@gt-usa.com